After the User Test on (2/8), there were several components needed upgrade:
- structure – nonexistent and/or not convincing nor appealing
- book mechanisms is not working
Week 12:
8/8:
- meeting with lecturer to discuss and plan the book mechanism
- lecturer helped with assembling the metal structures that required power tools
mechanism update: 3D printed dial with micro switch, some stoppers may be applied
![](https://cdn.hackaday.io/images/830901535909288181.png)
![](https://cdn.hackaday.io/images/4607431535909288861.png)
9/8:
- 3D printing and trial-and-error-ing the measurement to fit to the book
- animation work still going on
- copywriting work on the book
Week 13:
13/8:
- laser cut the remaining book structure, the bones, to make the hollow space to fit the sensors
- continue working on the interact-ables (3D printing work)
- animation work still going on
- copywriting work on final messages
14/8:
- printed the finalised pages
![](https://cdn.hackaday.io/images/2276191535903322683.jpg)
- sticking it to the woodpieces
![](https://cdn.hackaday.io/images/7255201535903466858.jpg)
- measuring & make cuts on corrugated boards for the structure
we need a few panels to cover up the front & back, sides & top
15/8:
- hand cutting and laser cutting corrugated boards to desired measurements
- cutting holes into the plywood to attach sensors and interact-ables
- animation needs some fine tune and refining
16/8:
- getting a PC for display and run Processing (spoiler: it didn't work, we didn't have converter for VGA to HDMI; backup plan required)
- fine tuning of animation
- sticking the wooden frame, now they've got hollow spaces (spoiler: we made a mistake, we didn't put in the nut for the screws later, DOH!)
this day we're overnight-ing at college for another projects needed to be submitted in 4 days and required many hours to complete, there wasn't much progress after this.
Week 14:
21/8:
we're just done with our other projects, today is a rest day, preparing for an overnight tomorrow
- fix the nonexistent slot for the nut that we forgot to put on beforehand
- redid the acrylic by putting car tint film to prevent reflection instead of the blue filter paper because it's inconsistent and bubbly
22/8 (public holiday) - 23/8 :
wow no holiday, bye holiday
- full day working on the book and measuring the structure
- attaching sensors to where they belong and their corresponding interact-ables
- fine tuning animation
- structure work
- copywriting work
- coding work
- wiring work (spoiler: too messy our lecturer needed to hands on)
final look in case something bad happens, this is working perfectly, btw
23/8 (final client review):
- lecturer fixed the wiring
- final touch wiring & stickers placing
- screw everything together
- animation is complete
- structure is 80% complete, need some fine tuning
client review result:
- a few bug (major bug) in the code
- animation needs some final fine tuning here and there
OVERNIGHT pt.2
23/8 - 24/8:
- too tired there are a lot of nap breaks
- tried fixing the code but to no avail
- animation is complete
- structure is complete
- in the morning our lecturer came up with solutions for the code (much thanks awlolo)
- problems solved
- wait until 10pm to bring over installation to Sunway Pyramid for the setup
OVERNIGHT pt.3
24/8-25/8:
- worked whole night (with slacks and McD break hehe thanks) to setup and try the user journey over and over again to make sure it works, but too bad nothing is perfect.
![](https://cdn.hackaday.io/images/1283641535907070499.jpg)
![](https://cdn.hackaday.io/images/5515021535907240706.jpg)
![](https://cdn.hackaday.io/images/5844561535907240957.jpg)
![](https://cdn.hackaday.io/images/6695301535907240954.jpg)
![](https://cdn.hackaday.io/images/9257091535907242727.jpg)
![](https://cdn.hackaday.io/images/2157191535907243517.jpg)
![](https://cdn.hackaday.io/images/2307081535907246694.jpg)
25/8 (Exhibition day):
- needs to reset(code word: banana) after a few times because it gets laggy
- exhibition went well, OK
- fix the instructions on the animation for the next day, it was rather unclear at first
before edit (no instructions):
![](https://cdn.hackaday.io/images/8827931535909427535.png)
after edit (with instructions):
![](https://cdn.hackaday.io/images/7996911535909441583.png)
exhibition gallery:
![](https://cdn.hackaday.io/images/1608951535908553569.jpg)
![](https://cdn.hackaday.io/images/8819691535908554309.jpg)
![](https://cdn.hackaday.io/images/1011951535908554464.jpg)
![](https://cdn.hackaday.io/images/2441081535908554526.jpg)
![](https://cdn.hackaday.io/images/4357901535908554537.jpg)
![](https://cdn.hackaday.io/images/7861281535908554611.jpg)
![](https://cdn.hackaday.io/images/4120991535908555231.jpg)
![](https://cdn.hackaday.io/images/8764601535908556149.jpg)
![](https://cdn.hackaday.io/images/1699551535908556522.jpg)
![](https://cdn.hackaday.io/images/8040201535908556506.jpg)
![](https://cdn.hackaday.io/images/152631535908556777.jpg)
![](https://cdn.hackaday.io/images/5990311535908556713.jpg)
26/8 (final day):
- on the last day after some code rigging and animation change, it looked like this
- we figured it was too much work to fix the entire code, so we just went with it and rig the code just one more day
we allow people to write on our panels so here are a few words from our friends, strangers, even fellow seniors:
![](https://cdn.hackaday.io/images/4260291535909460523.png)
![](https://cdn.hackaday.io/images/3577221535909462700.png)
after it ended, we dismantled and left the place, went to boston lala, and ended the day.
to end on a high note, we went for a nice lunch the next day, to celebrate everyone's hard-work-paid-off, yeay!
our video journal:
(unlisted link)