WEEK 7
Monday, 02/07/2018
Met up for 9th Group Discussion.
Officially commence construction planning.
Master list of questions we asked ourselves to properly map out our project plans on mahjong paper™:
THINGS TO ASK CLIENT
- Charity for Donation Box?
- Who is going to supervise/handle collection + distribution?
- Project deadlines
- Display duration
THINGS TO ASK BUILDING CREW
- How big is service lift? Do we need to separate the structure into segments?
CREATING THE INSTALLATION
A) Mechanism
- What mechanism do we use for each interactable item?
- What does the mechanism need? (wiring? battery? circuits?)
- Where do the mechanisms go inside the installation?
B) Structure
- What is the updated blueprint plan for the structure?
- What are the materials that the client has?
- What are the materials that we still need?
- What are the building tools that we need?
- Where are we going to build the structure?
- Do we need to design it so it can be disassembled?
C) Items
- What is the final list of interactable items?
- Are the physical objects tinker-able? (do we need to craft a fake one? or use skeleton?)
- Where are we going to buy/source these items?
- When are we going to buy them?
- How much are they going to cost?
- How to theft-proof?
Once everything was mapped out properly, the following two days were dedicated to surveying the items on our shopping list.
Thursday, 05/07/2018
AM: Continued shopping list survey online, outlined weekly schedule, begin coding research. HOD's appointed for ease of organisation and execution, though members' obligations are not limited by their appointed work areas.
- Project Manager (Carla)
- Communications (Carla)
- Copywriting (Carla)
- Technical (Yong Jie)
- Audio & Video (Felecia)
- Logistics (Natalie)
PM: Visited client's workshop.
- Surveyed materials needed to build structure i.e. wood planks, boards, frames, etc.
- Took measurements of confirmed recyclables.
- Further discussed building plans; workshop liaison expressed need for more detailed structure technical plan in order for workshop crew to assist in building; we promised to send it over before our next visit.
Friday, 06/07/2018
Met up for 10th Group Discussion.
- Took a 'field trip' to Pudu to survey LED strip prices.
- Returned to FabLab to discuss structure dimensions for updated technical plan
Discussions