GERMANY: 1. SprengV Amendment 1
Blasting machines
- mechanical requirements
- The blasting machine must work reliably
- The blasting machine must have a robust and closed enclosure
- All parts of the blasting machine must be undetectable
- The design must complicate unauthorized operation
- electrical requirements
- The blasting machine must have massive connection terminals. They must not be hollow and the diameter must be a minimum of 4mm. Protection against touching electric shock must be given.
- Between the terminals there must be an isolation barrier that overtops the connection surface for at least 8mm.
- Isolation between electrical parts and the housing must be at least 1000V or the double working voltage.
- Isolation parts must comply with the state of the art
- Capacitor blasting machines have to ensure that the capacitor is discharged after blasting.
- An interlock must ensure that triggering is only possible if the full electrical power (energy) is available.
- performance
- type A
- After 1ms the current must reach at least 1A. From the beginning until falling below 1A, the impulse must be at least 4mWs/Ω.
- limiting resistance
10 ignitors 60Ω 20 ignitors 110Ω 30 ignitors 160Ω 50 ignitors 260Ω 80 ignitors 410Ω 100 ignitors 510Ω 160 ignitors 810Ω 200 ignitors 1010Ω
- type U
- After 1ms the current must reach at least 2A. From the beginning until falling below 1.5A, the impulse must be at least 18mWs/Ω.
- limiting resistance
10 ignitors 55Ω 20 ignitors 90Ω 30 ignitors 125Ω 50 ignitors 195Ω 80 ignitors 300Ω 100 ignitors 370Ω 160 ignitors 580Ω 200 ignitors 720Ω
- type HU
- After 1ms the current must reach at least 30A. From the beginning until falling below 15A, the impulse must be at least 3.3Ws/Ω.
- limiting resistance
20 ignitors 15Ω 80 ignitors 50Ω 160 ignitors 100Ω
- type A
- other requirements
- In regard to protection against firedamp the blasting machines must comply to the state of the art.
- The ignition current pulse must not be longer than 4ms. After triggering the recharging of the capacitor, triggering a second pulse must be impossible.
Blasting circuit continuity tester
- general requirements
- The current source must not be accessible
- The voltage of the current source must be lower equal 12V
- The test current must be less than 25mA
- There must be protection resistors to limit the current in a single failure case to 50mA
- special requirements for Ω–meters
- The accuracy must be 1.5% of the full range
- The zero point should be regulated
- A 10% deviation of the current source voltage must not influence the measurement accuracy
AUSTRIA: Regulation for blasting for mining
Very similar to the GERMAN version.
- Between the terminals there must be an isolation barrier that overtops the connection surface for at least
810mm. - A performance sheet must be on the housing
- type description
- manufacturer and manufacturing site
- site number
- manufacturing date
- limiting resistance
- blasting voltage and capacitor capacity
US: eCFR / Title 30 / Chapter 1 / Subchapter K / Part 56 / Subpart E / Electric Blasting
- Shunting
Except during testing —- Electric detonators shall be kept shunted until connected to the blasting line or wired into a blasting round;
- Wired rounds shall be kept shunted until connected to the blasting line; and
- Blasting lines shall be kept shunted until immediately before blasting.
- Firing devices
- Power sources shall be capable of delivering sufficient current to energize all electric detonators to be fired with the type of circuits used. Storage or dry cell batteries are not permitted as power sources.
- Blasting machines shall be tested, repaired, and maintained in accordance with manufacturer's instructions.
- Only the blaster shall have the key or other control to an electrical firing device.
- Circuit Testing
A blasting galvanometer or other instrument designed for testing blasting circuits shall be used to test each of the following:- Continuity of each electric or electronic detonator in the blasthole prior to stemming and connection to the blasting line.
- Resistance of individual series or the resistance of multiple balanced series to be connected in parallel prior to their connection to the blasting line.
- Continuity of blasting lines prior to the connection of electric or electronic detonator series.
- Total blasting circuit resistance prior to connection to the power source.
Discussions
Become a Hackaday.io Member
Create an account to leave a comment. Already have an account? Log In.