So far so good. The structure, flooring and elevator design has held up. Per a previous post I did some refinements on the stairs. Between levels 100-120 the cable trays that dropped down to a box needed to be shortened. The lights are looking good. I realized that from these levels up each level has 12 lights, not 13. The first two levels had a light over the stairs and I was continuing that. From now on I will only add 12 lights per level. Before I hang the ECS pipes under the level 120 floor I will need to add the ECS pipes to the outside of side 2.
The ECS pipes are in, including the two (E7 & E11) that go over towards Swing Arm #2. In the first picture you can see that it takes some doing to get things lined up before gluing. I only used 6 hanger brackets because of other various parts and wires in the way. I had some minor parts updates to get the pipes just right.
Section 2 of the tower is now complete except for Swing Arm #2. Notice the camera platform at level 100.
Swing Arm #2: The parts are designed and printed. Working on assembling them. Black wire is used to model the cabling. I still need to paint some flexible tubing and connect up the end, get the arm attached and attach the walkway.
Discussions
Become a Hackaday.io Member
Create an account to leave a comment. Already have an account? Log In.